Current Rail Projects

Phase 1 - Northern Interchange Yard Expansion

12,433′ of abandoned track in the old B&O Yard reconditioned and put back into service

2,800′ of new connector tracks were constructed extending four tracks and tying them into the abandoned B&O tracks

And an additional 1,000′ of new track was constructed on the west end of the restored tracks to fully maximize storage capacity

Atlantic Forest Products

A new 2,800′ rail spur was constructed to serve the AFP facility

Other Major Track Projects

21,276 feet of yard tracks were put back into service in A-Yard, Northern Interchange, and M-Yard

6 turnouts and 4,000′ of track was rebuilt in the 1100-Yard